Guys I have a question about MRP. I am attaching the documents too for your reference.In MD04 I see the Pur Req which has requirements of 720 EA. Material has rounding value of 360 but when I see the future requirements I don't see anything which should generate requirements for 720. I am attaching MD63,MMBE,and MM04 screen shots for you reference. Following are the values from MRP1 .We use APO and values in APO matching MD63.
Material 112HGRFG1
Plant 1024
Base Unit of Measure EA each MRP group Z001
Purchasing Group ABC Indicator C
Plant-sp.matl status Valid from
MRP Type PD MRP
Reorder Point 0 Planning time fence 0
Planning cycle MRP Controller 999
Lot size TB Daily lot size
Minimum Lot Size 0 Maximum Lot Size 0
Maximum stock level 0
Assembly scrap (%) 0.00 Takt time 0
Rounding Profile Rounding value 360
Unit of Measure Grp