Hi,
After i run MRP with a weekly lot sizing procedure, avaiability date = start of the period, the MRP groups all planned orders of the week at the first requirements date of that week.
But what i need is to put that group of the planned orders in the last working day of the week before.
For example:
Week | Friday Week n | Week n+1 | ||||
Ind. Requirements | 0 | 1 | 1 | 1 | 1 | 1 |
Planned order | 5 |
Can you please help me how to solve this issue.
Thanks in advance.
Mike