Hello All
We have a typical business case, We are not using self life functionalality in SCM system. But we would like to consider the stocks based on the expiry date.
Example
Forecast :1000 cs from customer 1
Forecast : 400 cs from cusomer 2
Total Forecast is : 2500 Cs
Stock : 500 CS ( out of 500 cs 50 cs have 18 month expiry date and rest of 450 cs have 12 month expiry date)
so customer 1 will accept stocks of only 18 month and above
and Customer 2 will accept stocks of 12 month and above
So during normal Location heuristic the net requirement calculation output will be 900 CS. ( 1400-500 = 900 CS)
But we would like have resluts like as below
(1000- 50 = 950 ) & (400-450=0) meaning we want system to propose requirment 950 cs for customer 1 and nothing for customer 2 beacuse sufficiant stock of 12 month expiry.
Is there any way to plan like this in SNP. Any help or hints will be great help.
Best Regards