Hi Experts:
Did anyone worked on the below highlighted scenario instead of linking an Internal order manually?
You can have the system create new orders automatically, or you can assign existing orders to the appropriation request. When you use automatic creation, the data is adopted from the appropriation request. You can specify if the plan values are adopted completely or partially during this automatic creation.
When creating multiple measures, the system ensures that no more than 100% of the plan values are transferred to the measures in total, and that (sub)calculations are only transferred once.